What's Gouin on 2/27/09?

After years of planning and months of work, we finally took occupancy of our new SIP/modular hybrid home in early 2009.  After living in the home for several weeks we have had the opportunity to put the house through its paces.  Now I can say with certitude, "Why wouldn't everyone want to build this way?"

Despite only being in the house for a few weeks, we've had the opportunity to experience living in the house through rain, snow, and outside temperatures ranging from ~0ºF to ~50ºF.  Here are a few observations:

Penn Lyon Homes - The Good, The Bad, and The Ugly - Part 1

What's Gouin On 11/13/2008?

Sorry everyone, there has been a lot going on with our project.  Between work, home life, and working on the house I have been burning the candle at both ends and have had little time to write.  I have a lot of things to report on since my last update.

What's Gouin on 9/21/2008?

Progress has been slower than expected, but we are making progress.  Much of the electrical work has been completed, and we are hoping to get power to the house this week.  We are simply waiting on the electrical inspector to give the okay and the electric company to connect the lines.

Scales Well and Pump installed our well pumps, tanks, and variable speed controls.  Once we have power, we will have water.

What's Gouin On 8/24/08?

It's been a while since I provided any sort of update except in pictures. Things were slow today so I figured I'd take some time to catch you up.

It has been exactly one month since the modules were set on the foundation. We continue to wait for Penn Lyon to pick up their trailers in order for us to backfill the left side of the foundation and dig the electrical trench.

We are also waiting for the Penn Lyon service crew. They need to:

1. Replace the front main roof (misaligned shingles)
2. Complete roof drip edge (sections missing)

Unavoidable Setbacks

I was going to avoid writing about this, but after much contemplation, I came to the conclusion that I should. I feel it important for everyone to understand that every building project has its unavoidable problems and setbacks, and this project is no different.

Pictures Worth 1,000 Words

I have been way to busy to write much lately.  Hopefully the pictures provided will be worth more than any words I could write.  Please enjoy...

http://www.gouingreen.com/node/30

Ed 

Are we the World's First True SIP / Modular Hybrid House?

Before we began this adventure I did extensive Internet research looking for someone who has built a home like this before (using SIPs in a modular factory) because I wanted them to build one for us.  I had no luck.

A Foundation In One Day

I visited the Oasis precast foundation factory on Monday (6/9/08) and watched our foundation being poured. I was fascinated by their process, and the thoughtful detail that goes into their product. This product already uses 70% less concrete than a poured wall, provides a true R10 system, includes mold-proof wallboard, and it does so with very little to no waste. The forms look impressive. I can't wait to see it installed tomorrow (6/12/08).

Modular Foundation Installation - You Are Invited

Our Oasis foundation is scheduled to be installed on June 12, 2008.  For those of you in the area who are interested in viewing the installation, the property address is 100 Perry Street, Douglas, MA.  We will likely be there most of the day.  Anyone is welcome.

The attached picture shows what the foundation hole looks like today. 